UNION COUNTY, N.C. — A sewer capacity shortage has halted growth across Indian Trail and Stallings after the Crooked Creek Water Reclamation Facility reached its maximum treatment capacity.

Union County Water confirmed it can no longer process wastewater permits for new construction along the U.S. 74 corridor, leaving 19 pending development projects awaiting review in limbo.

The freeze impacts proposed commercial developments, municipal improvements and health care facilities.

Indian Trail Town Manager Adam McLamb said he is working with the town council to resolve the infrastructure bottleneck. “How do we, you know, provide capacity and sewer for those businesses so the town can continue to grow?” McLamb asked.

McLamb said the suspended proposals encompass multiple commercial and industrial sectors throughout the community.

“We know of projects in hospitality, recreation, industrial, small business, even a hospital. A specialized hospital that was going to come to Indian Trail for rehab. That all don’t have capacity, and they’re all trying to figure out what they’re going to do,” McLamb said.

Public initiatives have also stalled under the permit halt, including plans to construct a community center featuring public restrooms at Chestnut Park. Jeff Hamrick, an Indian Trail native and resident, questioned the stoppage.

“Even something like that is just crazy to hear … that they are trying to bring something that would be nice to the community. But oh, we’ll be held up because we can’t have a bathroom,” Hamrick said. “What are we doing?”

Indian Trail is currently in the middle of a major downtown investment project, raising concerns about broader economic effects.

“It’s great to have the growth here,” Hamrick said. “It’s great to have the people here and bring the economics to that. That also needs to be supported.”

Hamrick noted that developers should play a role in finding solutions. To keep growth moving forward, McLamb said the town is actively speaking with several developers about potential alternatives, including individual septic systems or independent wastewater treatment plants.

The infrastructure constraint similarly affects neighboring Stallings. Stallings Town Manager Alex Sewell said Union County notified the town about the capacity restrictions on Oct. 30.

“We’re still working with Union County Water to confirm the status of individual development projects and determine which ones may be affected by the capacity restrictions,” Sewell said.

Union County officials stated that substantial capital projects are planned to address regional needs.

“Union County recognizes the importance of maintaining adequate wastewater capacity to support our community,” the county said in a statement. “We are making substantial investments in our wastewater infrastructure, with $216 million in wastewater projects identified in our Capital Improvement Plan.”

County officials declined an interview at this time, explaining that the capacity halt applies solely to the Crooked Creek facility.

“Although the Crooked Creek Water Reclamation Facility has reached its current treatment capacity and is unable to accommodate applications for new development, Union County Water will continue to accept and process wastewater capacity applications in our other sewer service areas, according to our policies and procedures,” the county statement said.

The county stated that staff members will continue collaborating with applicants while upholding state regulations.

“Our staff remains committed to working directly with permit applicants to address questions regarding projects currently under review and ensuring compliance with state wastewater treatment capacity limitations,” the county said.

Earlier this year, Union County commissioners discussed potential expansion options for the Crooked Creek facility. Discussions indicated that a possible expansion could cost millions of dollars and require upward of a decade to complete.